BOARD OF WORKS AND SAFETY
Special Meeting
August 8, 2022
4:30 PM
StoneGate Arts & Education Center
931 15th Street
AGENDA
Call To Order
New Business
1. Receiving and Opening; And Acceptance Of Bids – Spider Creek Pump Station and Storage Tank for Sanitary Sewer Overflow Project; And Overall Sanitary Sewer Improvements – Misty Adams
• Opening of bids 2.5 million bolted epoxy coated 110 ft by 37 ft steel tank with
accessories
• Opening of bids flushing system for 2.5-million-gallon tank
• Opening of bids for (1) 600 KW, (2) 125 KW, and (1) 30 KW generator with all piping, foundation, installation, and stainless transfer switch
• Opening of bids for gravity sewer line from 6th St to O Street
• Opening of bids for 14" force main from Spider Creek lift station to Denson Avenue
• Opening of bids for 25MGD fine screen system, (2) 127 HP 12"pipe discharge
submersible pumps, (3) 188 HP 20" pipe discharge submersible pumps, and (3) alternate I50 HP 20" pipe discharge with start up and training
2. Resolution 3-2022 – Support Of Application Of READI Grant – Misty Adams
3. Discussion
4. Adjourn